Lucinda - Tropical Cyclone Yasi Re-development Project

Array
(
    [0] => steel-detailing
)
  • Project Type: steel detailing |
  • 3D modelling and detailing of all temporary and permanent works.
  • Temp works includes all access platforms, walkways, lifting jigs, pile clamps.
  • Permanent works includes
    • 53m long single welded frame Fender Truss.
    • Cross Under Walkways
    • Dolphin Berth Access BD6 & BD8 & BD7
    • Northern Walkway
    • Ship loader Secondary Strong Point
    • Northern Strongpoint
    • Wharf Roadway Access Frame
  • Installation 100% with no re-work required.

Back to Projects

(07) 4772 6070
4 Somer Street, Hyde Park 4812
PO Box 3221 Hermit Park, QLD 4812

Email Us linkedinLinkedIn
ASI AISD